Construction Update for Week of 10/28/19

Project traffic updates for next week: Burlington Residential Sewer – No work expected next week. S. Hoyt Residential Sewer – Grinder pump installation/restoration throughout the project area with limited impacts. CSO 028 Monroe St. – Monroe Street closed from Wysor Street to Gilbert Street for sewer construction.  Gilbert Street closed from Monroe Street to Vine…

Construction Update for the Week of 10/21/19

Project traffic updates for next week: Burlington Residential Sewer – No work expected next week. S. Hoyt Residential Sewer – Grinder pump installation/restoration throughout the project area with limited impacts. CSO 028 Monroe St. – Monroe Street closed from Wysor Street to Gilbert Street for sewer construction.  Gilbert Street closed from Monroe Street to Vine…

Construction Update for the Week of 10/14/19

Project traffic updates for next week: Burlington Residential Sewer – No work expected next week. S. Hoyt Residential Sewer – Grinder pump installation/restoration throughout the project area with limited impacts. CSO 028 Monroe St. – Monroe Street closed from Wysor Street to Gilbert Street for sewer construction.  Gilbert Street closed from Monroe Street to Vine…

Construction Update for the Week of 09/30/19

Project traffic updates for next week: Burlington Residential Sewer – No work expected next week. S. Hoyt Residential Sewer – Grinder pump installation/restoration throughout the project area with limited impacts. CSO 028 Monroe St. – Monroe Street closed from Wysor Street to Gilbert Street for sewer construction. Petty Road Sewer Repair – Lane restrictions along…

Construction Update for the Week of 9/23/19

Project traffic updates for next week: Burlington Residential Sewer – No work expected next week. S. Hoyt Residential Sewer – Grinder pump installation/restoration throughout the project area with limited impacts. CSO 028 Monroe St. Lift Station – Monroe Street closed from Wysor Street to Gilbert Street for sewer construction. Petty Road Sewer Repair – Lane…

Construction Update for the Week of 9/16/19

Project traffic updates for next week: Burlington Residential Sewer – No work expected next week. S. Hoyt Residential Sewer – Restoration activities throughout the project area with limited impacts. CSO 028 Monroe St. Lift Station – Monroe Street closed from Wysor Street to Gilbert Street for sewer construction. Petty Road Sewer Repair – Lane restrictions…

Construction Updates for Week of 8/19/19

Project traffic updates for the week of August 19, 2019: Elgin & McGalliard Storm Sewer – Some lane restrictions on McGalliard between Doctor MLK Jr Blvd. and N Elgin Street. N Elgin St. just south of McGalliard is now open with minor lane restrictions. S. Hoyt Residential Sewer – Restoration activities throughout the project area…

Muncie Sanitary District announces two relocation projects

MUNCIE, INDIANA — Muncie Sanitary District recently announced two new relocation projects for some of its offices and departments. These projects are expected to improve operational efficiencies and save on energy and transportation costs. The first project would relocate the District’s Sanitation Department to Dr. Martin Luther King Jr. Boulevard. The department is currently located…

Construction Updates for Week of 8/5/19: Monroe Street closed from Wysor to Gilbert

Project traffic updates for the week of August 5, 2019: Burlington Residential Sewer – Minor and temporary lane restrictions throughout the project. Elgin & McGalliard Storm Sewer – Some lane restrictions on McGalliard between Doctor MLK Jr Blvd. and N Elgin Street. N Elgin St. just south of McGalliard is now open with minor lane restrictions.…