Construction Update for the Week of 9/23/19

Project traffic updates for next week:

  1. Burlington Residential Sewer – No work expected next week.
  2. S. Hoyt Residential Sewer – Grinder pump installation/restoration throughout the project area with limited impacts.
  3. CSO 028 Monroe St. Lift Station – Monroe Street closed from Wysor Street to Gilbert Street for sewer construction.
  4. Petty Road Sewer Repair – Lane restrictions along N. Petty Road and W. Petty Road between Mockingbird Lane and Robinwood Drive for sewer repair.
  5. High Street Siphon Repair – High Street Bridge/Wheeling Avenue between University Blvd. and Franklin/Wysor Street will be restricted for sewer construction across White River.  One lane of traffic in each direction on High Street/Wheeling Avenue will be maintained at all times.  The project is scheduled to be completed by mid-October.  Attached is an exhibit showing the impacted traffic area.