Construction Update for the Week of 9/16/19

Project traffic updates for next week:

  1. Burlington Residential Sewer – No work expected next week.
  2. S. Hoyt Residential Sewer – Restoration activities throughout the project area with limited impacts.
  3. CSO 028 Monroe St. Lift Station – Monroe Street closed from Wysor Street to Gilbert Street for sewer construction.
  4. Petty Road Sewer Repair – Lane restrictions along N. Petty Road and W. Petty Road between Mockingbird Lane and Robinwood Drive for sewer repair.
  5. High Street Siphon Repair – High Street Bridge/Wheeling Avenue between University Blvd. and Franklin/Wysor Street will be restricted for sewer construction across White River.  One lane of traffic on High Street/Wheeling Avenue will be maintained at all times.  The project is scheduled to be completed by mid-October.
  6. High Street Siphon Repair (Crane Erection) – White River Blvd. will be temporarily closed for 4-8 hours on Saturday, September 14th for crane erection.  The closure will be from Wheeling Avenue to the Washington Street Bridge beginning at 7:00 a.m.  Detour routes will be posted with additional information included in the attached exhibits.