Project traffic updates for next week:

  1. Burlington Residential Sewer – Minor and temporary lane restrictions throughout the project for punchlist work.
  2. Elgin & McGalliard Storm Sewer – Right eastbound lane/shoulder closure on McGalliard Road for storm sewer construction.  Temporary flagging and lane restrictions on Elgin Street for storm sewer construction.
  3. S. Hoyt Residential Sewer – Exhibit attached showing the location of sanitary force main and service lateral installation requiring lane restrictions.
  4. CSO 028 Monroe St. Lift Station – Temporary lane closures of Wysor Street and Madison Street for asphalt restoration.  Monroe Street closed from Wysor Street to Gilbert Street for lift station construction.