Construction Update for the Week of 12/10/18: N. Linden St will be Closed for Approx 2 more Weeks, & Lane Restrictions on Edgewood Dr

The following projects are expected to have traffic impacts next week:

1. Burlington Residential Sewer – Exhibit attached showing the location of sanitary force main installation with minimal traffic impacts anticipated.
2. Elgin & McGalliard Storm Sewer – Flagging operations with partial disruption to normal traffic on Elgin Street and McGalliard Road for subsurface exploration to locate existing utilities.
3. CSO 009 Storm Sewer – N. Linden St. just north of White River Blvd. will be closed for approximately 2 additional weeks to complete storm sewer installation in the alley north of Holy Trinity Church. Utility relocations have delayed completion of this project.
4. S. Hoyt Residential Sewer – Lane restrictions will be required on Edgewood Dr. between Old SR 67 and Delaware Dr. for force main and service lateral installation.

2018-12-10 Street Closures – Burlington Sewer System