Construction Update for the Week of 04/08/19: Monroe St closed btwn Wysor & Gilbert, Wysor St btwn Elm St & Hackley St closed

The following projects are expected to have traffic impacts next week:

  1. Burlington Residential Sewer – Exhibit attached showing the location of grinder pump installation between CR 300 S and Inlow Springs Rd requiring lane restrictions.
  2. Elgin & McGalliard Storm Sewer – No impacts next week.
  3. S. Hoyt Residential Sewer – Exhibit attached showing the location of sanitary force main and service lateral installation requiring lane restrictions.
  4. CSO 028 Monroe St. Lift Station – Monroe Street will be closed between Wysor Street and Gilbert Street for lift station installation.  Wysor Street between Elm Street and Hackley Street will be closed for sanitary force main installation including the intersection of Madison Street.  Reference attached exhibit for impacted locations.  Detour Signage has been installed for impacted streets.