Madison Street Sewer Rehabilitation- Maintenance of Traffic Update

Posted by: Jason Donati on Thursday, February 22, 2018

Bowen/Layne Inliner will be working on Thursday, February 22nd, 2018 to cut out a pipe blockage in the Madison Street combined sewer between Howard Street and Charles Street. This will involve temporary lane closures for access to the sewer. Traffic will be maintained at all times in both directions.

Pipelining will also be scheduled in mid-March to complete sewer rehabilitation on Madison Street between the underpass and Gilbert Street in advance of the City’s street resurfacing project scheduled to begin in March.