For the Week of 05/15/17: Construction Update for Madison Street Underpass & CSO 028 Separation Project

Posted by: Jason Donati on Monday, August 21, 2017

Attached is a revised exhibit showing street impacts due to construction in the CSO 028 and Madison Street Underpass Storm System project areas for public notification.

Work in the CSO 028 project area will continue next week with construction of the White River Interceptor re-route near the intersection of Myrtle Avenue and Elm Street. Minimal traffic impacts are expected with this work.

Work at the Madison Street pump station site will continue within the fence with temporary lane restrictions on Howard Street and Monroe Street. Lane restrictions are not expected on Madison Street for next week. Work will continue for force main installation on Adams Street. At least one lane of traffic will remain open on Adams Street between Walnut Street and Monroe Street with detour signage for any lane restrictions. Next week, Adams Street lane restrictions are expected between Madison Street and Monroe Street and between Walnut Street and Mulberry Street.

Work will also continue for the Tillotson/Kilgore force main with minimal traffic impacts along the north side of Kilgore Avenue and the west side of Tillotson Avenue for service installations, restoration, and final lift station improvements.