Construction Update for the Week of 12/25/17: Madison St Underpass Storm System Project, CSO 028, & McKinley Stormwater Project

Posted by: Jason Donati on Thursday, December 21, 2017

Here is a revised exhibit showing street impacts due to construction in the CSO 028 and Madison Street Underpass Storm System project areas for public notification. No work is scheduled for next week due to the holidays.

For the week of January 1st:

Work in the CSO 028 (Area 2) Project will continue in the McKinley stormwater pond area near the intersection of Myrtle Avenue and Elm Street with minimal traffic impacts. The alley to the east of Elm Street, running south from Columbus Avenue, will be closed for storm sewer installation. Race Street between Madison Street and Elm Street will be closed for storm sewer installation.