Construction Update for the Week of 02/12/18: Limited Traffic Impacts & Temporary Lane Closure near Madison St Underpass

Posted by: Jason Donati on Friday, February 9, 2018

Here is a revised exhibit showing street impacts due to construction in the CSO 028 and Madison Street Underpass Storm System project areas for public notification.

Work in the CSO 028 (Area 2) Project will continue in the McKinley stormwater pond area near the intersection of Myrtle Avenue and Elm Street with minimal traffic impacts.

A temporary lane closure is scheduled on Madison Street just north of the Madison underpass to install rip rap on the embankment adjacent to the storm pump station site. This work is scheduled for Monday (2/12) and is expected to be one day only with two-way traffic maintained at all times.

Periodic lane closures on the White River Blvd at Pauline Avenue are expected to unload materials for the Pauline Lift Station outfall pipe improvement. The greenway will also be detoured at this location during pipe installation. Traffic will be maintained at all times on White River Blvd.