Construction Update for 11/20/17: Madison St Underpass, CSO 028, and Wysor St Closure

Posted by: Jason Donati on Friday, November 17, 2017

Here is a revised exhibit showing street impacts due to construction in the CSO 028 and Madison Street Underpass Storm System project areas for public notification.

Work in the CSO 028 (Area 1) Project will continue along Wysor Street between High Street and Walnut Street next week and continue through December 2017. Wysor Street between Walnut Street and High Street will continue to be closed next week for restoration work. In addition, the northbound lane of High Street will be closed near City Hall for restoration work. Weather delayed restoration work this week.

Work in the CSO 028 (Area 2) Project will continue in the McKinley stormwater pond area near the intersection of Myrtle Avenue and Elm Street with minimal traffic impacts. The alley to the east of Walnut Street, running south from Columbus Avenue, will be closed for one week for asphalt installation. The alley to the east of Elm Street, running south from Columbus Avenue, will be closed for storm sewer installation.